Large order for a batch plant

Company Şişecam decided to construct a new float glass plant for two furnaces, each 750 to/day, in Alaboga (Tartastan) and hired ZIPPE Industrieanlagen once more for the execution of the batch plant.

The plant consists of:

train wagon unloading for mechanical and pneumatic raw material delivery
a separate sand storage
a batch plant with two weighing lines
an automatic cullet return system
a separate cullet storage including weighing.

Our scope of delivery includes the engineering for concrete and steel work, the delivery of the entire equipment, installation, electric control system, cabling and commissioning.

The factory will manufacture 230 000 tons of multi layered glass annually, 6 million square meters of mirror glass as well as 5 million square meters of window glass. In total, 620 new jobs will be created in the new manufacturing plant.

Source: Zippe/Şişecam